The building dealership Transparent in Porto contests demolition as an acquired outcome, claiming that the subsistence of the concession is still under judicial discussion.
© Wikimedia Commons/Manuel de Sousa
17/11/2026
by
Lusa
A concessionaire of the Building Transparent, in Porto, today contested that its demolition is presented “as an acquired outcome” in a public procurement procedure, when a lawsuit for its subsistence and extension of the concession still takes place in court.
In question the announcement, on 12 November, that the House of Porto, through the municipal company Go Porto, initiated a public procurement procedure for the preparation of a project for the demolition of the Transparent Building and the renaturalization of the International beach.
“The concessionaire [Hottrade] disputes the presentation of demolition as an acquired outcome, when the subsistence and extension of the concession are under discussion at the Administrative and Tax Court (TAF) of Porto. Hottrade defends the duration of the contract by 2054 and denounces the damage that these advertisements cause to its reputation and the trust of the installed operators ", criticizes today in a statement.
The dealership also wants to be clarified whether the Transparent Building has ever been designed to host the headquarters of Ocean Race – a company that owns the oldest race around the world – that will be installed in the Kasa da Praia, next to the same beach protected by the Coastal Waterfront Program and a few hundred meters away.
The Ministry of the Environment, the Portuguese Environment Agency and the mayor of Porto announced in April that the Transparent Building will be partially demolished, leaving only one floor at the beach level to serve as support for bathing practice.
“ Some 700 jobs, including 100 recently created jobs, and recent investments in the tune of EUR 200,000 are at stake. The position of the company is clear, the contracts are not extinguished by statement, nor are the rights erased by the launch of contests by stages ", highlights today in a statement the lawyer of the dealership, Pedro Mendes Ferreira.
In June, the dealership of the Transparent Building moved an action against the announced intention to demolish that building and “one-sided grant” of the concession.
On October 20, Hottrade requested the court to clarify by the municipality whether the Transparent Building “was, at any time, considered, studied or considered for provisional or definitive installation of The Ocean Race, the Ocean Museum or any structure associated with the project”.
At the end of September, the Port House approved the installation of Ocean Race's global headquarters in the Kasa da Praia building and the creation of the Ocean Museum.
The Programa da Orla Coastal Caminha/Espinho in force since 2021 identifies 46 critical areas and determines the protection of the International beach in Porto, with the demolition of the Transparent Building and the building where Kasa disco was working in Praia, returned since 2021.
In the request addressed to TAF do Porto, the lawyer of the concessionaire points out that the Transparent Building is “on the same maritime front and in the immediate surroundings” of “Kasa da Praia”, but that the municipality adopts a “materially diverse solution”, since “preserves the building, invests in its recovery and makes it available for a new use for a prolonged period, without any public utility and intended for private purposes of its convenience”.
“ If two buildings located on the same seafront were covered by the same coastal planning instrument and by demolition forecasts, it is not understood what the reasons and technical, environmental and public-interest assumptions justifying the preservation, recovery and prolonged provision of one of them and, at the same time, the intended reversal and demolition, even if partial, of the other”, points out.
It also considers it important to “determine whether the urgency expressed by the municipality in obtaining the availability of the Transparent Building has some connection with the need, now known, to provide facilities for The Ocean Race while the works of the Kasa da Praia take place”.
For this reason, Hottrade’s lawyer asks that all the documents and proposals on Ocean Race and the Ocean Museum be taken together, and that this data be appreciated, “in particular in the consideration of public and private interests”.
In the reply to the application, dated 21 October, and to which Lusa had access today, the TAF determines that the House of Port be notified “to rule on the possible provisional or definitive installation of The Ocean Race, the Ocean Museum or any structure associated with the project”.